Sunday, February 21, 2016

ST REGIS PROJECT - CAPITAL PLACE










0
0
ST REGIS JAKARTA
PROJECT WILL COMPLETE BY 
JUNE 30, 2015 !!!!
0



0
Contents


A.Project Update
   A.1     Scope of Main Contractor
   A.2     Site Progress Photograph
   A.3     Piling Work Progress
   A.4    Main Contract Tender
   A.5     Mock Up 
   A.6     Tender Schedule for All Packages
   A.7     Project Milestone
   A.8     Design Status
   A.9     Site Logistic Layout Plan
   
CONTENTS
CONTENTS


A.Permit and Licenses
   B.1     Achievement & Target
   B.2    Back Access Road    C.1 Loan agreement    
Loading...



      A.   PROJECT UPDATE
ST REGIS JAKARTA    -  section A
0



ST REGIS JAKARTA
A.1. SCOPE OF MAIN CONTRACTOR
Main Contract Works:

Fixed price lump sum contract
Mock up room by main contractor
Earthworks, concrete works, structural steel work, roofing, waterproofing, block work and basic finishes.
MEP ,  Facade and all other packages also by main contractor as long as pricing is competitive.
Coordinate the overlap piling contract works (ACSET)
Coordinate ground anchor installation during basement excavation (VSL)
0
Loading...



ST REGIS JAKARTA

A.2. SITE PROGRESS PHOTOGRAPHS AS OF 22 APRIL 2013
PILING ACTIVITY ON SITE 
0



ST REGIS JAKARTA
‘D’ wall panel fabrication in progress
Rebar stock yard
‘View of Site From Top of Ramp

‘View of Site From Jl. Gatot Soebroto side
0



ST REGIS JAKARTA
Service  crane supporting concreting activities
Sludge management hindred by rainfall impact and upon site operation
‘D’ wall excavation in progress along Jl. Gatot Soebroto side
‘D ‘ wall excavation in progress along Idola Tunggal side
0



ZONING AREA
A.3 PILE ZONING PLAN
OFFICE
HOTEL
PODIUM
0
ST REGIS JAKARTA



0
ST REGIS JAKARTA
A.3 PILING WORK PROGRESS AS OF 24 APRIL 2013

BORED PILE

















AREA
Qty Plan (pile)
Done
Remaining
Status
Ahead (+)
Behind (-)
(Days)
Target Completion
Contract Completion Date


ZONE - 1 (OFFICE)
414
314
100
+44 
15 May 2013
28 June 2013


ZONE - 2 (PODIUM)
193
28
165
-8
06 July 2013


ZONE - 3 (HOTEL)
194
24
170
+15 
13 June 2013


TOTAL
801
366
435
-8
06 July 2013











D-WALL
AREA
Qty Plan (panel)
Done
Remaining
Status
Ahead (+)
Behind (-)
(Days)
Target Completion
Contract Completion Date
ZONE - 1 (OFFICE)
32
17
15
+45 
14 May 2013
28 June 2013
ZONE - 2 (PODIUM)
26
0
26
-10
08 July 2013
ZONE - 3 (HOTEL)
28
6
22
+15 
13 June 2013
TOTAL
86
23
63
-10
08 Juli 2013




= NEW PILE
= EXISTING PILE
PILING LAYOUT PLAN
ST REGIS JAKARTA
Loading...



A.4 MAIN CONTRACT TENDER
#1 Submission Participants  
 (Opened 11 March 2013)
1.PT. Balfour Beatty Sakti
2.Grocon (JV) PT. Nusa Raya Cipta
3.PT. Leighton Contractor Indonesia
4.PT. Nusa Konstruksi Engineering
5.PT. SsangYong
6.PT. Tata Mulia Nusantara Indah 

#2 Submission Participants  
 (Opened 8 April 2013)
7.PT. Balfour Beatty Sakti
8.Grocon (JV) PT. Nusa Raya Cipta
9.PT. Leighton Contractor Indonesia
10.PT. Nusa Konstruksi Engineering
11.PT. SsangYong
12.PT.Tata Mulia Nusantara Indah  (Declined)



       
#3 Submission Participants  
 (Opened 22 April 2013) – 3 Best Price
1.Grocon (JV) PT. Nusa Raya Cipta
2.PT. Nusa Konstruksi Engineering
3.PT. SsangYong




Planned  
Main Contract Award 
30 April 2013



       

C O N F I D E N T I A L 
ST REGIS JAKARTA
0



Plywood Mock Up Study was completed on Oct 2012, inspected on 10 Dec 2012 and demolished on Jan 15 2013






Real Mock Up will be built
    by Main Contractor and 
  complete by 30 June 2013





       
ST REGIS JAKARTA

A.5 MOCK UP 
0



ST REGIS JAKARTA
A.6 TENDER SCHEDULE FOR ALL PACKAGES

TENDER SCHEDULE








No.
Tender Name
Start
Finish


1
Demolition Work 
Done
09 Jun '12


2
Ground Anchor and Soil Nailing Work
Done
08 Sep '12


3
Bore Pile and Retaining Wall Work
Done2
28 Nov '12


4
Main Contract
11 Jan '13
30 Apr '13


5
Façade (part of Main Contract scope if price competitive)
11 Apr '13
02 Jul '13


6
MEP (part of Main Contract scope if price competitive)
4 May ’13
27 Aug‘13


7
Associated equipment with MEP (part of Main Contract scope if price competitive)
28 Apr ’13
31 Mar ‘14


8
Building Maintenance Unit (Gondola) (part of Main Contract scope if price competitive)
23 Sep '13
03 Jan '14


9
Interior Works of Hotel (part of Main Contract scope if price competitive)
13 Dec '13
22 Aug '14


10
Interior works Office (part of Main Contract scope if price competitive)
15 Apr '14
15 Aug '14













0



ST REGIS JAKARTA
A.7 PROJECT MILESTONES









No.
Milestones
Date


1
LoA Main Contractor
30 Apr 2013


2
Completion of piling works zone 1 (Office Tower area)
15 May 2013


3
Excavation commencement
21 May 2013


4
Hand over all area from piling contractor
28 Jun 2013


5
Structure Ground Floor Office Tower complete
28 Dec 2013


6
Topping off Hotel
30 Jun 2014


7
PLN energized
10 Aug 2014


8
Completion of facade works - Hotel
24 Aug 2014


9
Topping off Office Tower
10 Dec 2014


10
Partial Taking Over BOH (on Bsmt 1 & Bsmt 2)
30 Jan 2015


11
Partial Taking Over FOH  (on Bsmt 1 M for staff & lev.3 for GM)
30 Jan 2015


12
Completion of facade works - Office Tower
06 Feb 2015


13
Project Completion
30 Jun 2015






0



CONSULTANT      CONCEPT     SCHEMATIC    DESIGN     TENDER    TARGET
               DEV             DOC    DATE
a.PCPA (Architect)    √     √    √                        
b. Airmas Asri (Architect)     √     √    √     √    5/2/13
c. Beca MEP/PT.BK     √     √     √     √    4/5/13
d. Beca Structure/Gistama     √     √     √     √    5/2/13
e. Champalimaud (ID)     √     √    progress        14/1/13
f.  Bensley Design (Landscape)       progress                23/10/13
g. CCW (Acoustic)     √     √     √     √    23/11/13
h. BSLD (Lighting)     √     √     √     √    18/11/13
ii.PT. LSI (QS)     √     √     √    progress
j. DSI-TTW (Façade)     √     √     √     √    29/4/13
k. PT. Geo Optima (Geotech)     √     √     √        
l. CKP Hospitality (Kitchen)     √     progress            26/12/13
m. Tess Neoh (SPA)     √     √    progress    
n. PT. Velo (IT)     √    progress            24/1/14
o. PT. Wiragardha (Security & FLS)     √     √    progress        15/11/13
p. PT. Airkon Pratama (Greenship)     √     √    progress    
q. VADI (Signage)    progress                24/3/14
r. CPP (Wind Tunnel)     √     √     √     √



       
ST REGIS JAKARTA

A.8 DESIGN STATUS
0



A.9  SITE LOGISTIC LAYOUT PLAN

JL. GATOT SOEBROTO
0
GRU & CM Site Office
Mock Up Location
Main Con Site Office

Ramp to site offices
Car park
VIP Car park
Motorcycle park
PT. Acset site office

Car park
ST REGIS JAKARTA



0
ST REGIS JAKARTA
A.9 GRU AND CM SITE OFFICE

2nd Floor
GRU Site Office
1st  Floor
CM Site Office



0
ST REGIS JAKARTA
A.10 PROJECT COST UPDATE

Based on DLS cost plan Dec 2012 with zero amount contingency.



0
PERMITS  -  section B
      B.   PERMITS AND LICENSES
0



ST REGIS JAKARTA
B.1 PERMITS AND LICENSES ACHIEVEMENT AND TARGET
               Status        Completion
KKOP            Approved        16/03/2012
Plot Ratio Increment        Approved        24/07/2012
SIPPT            Approved        23/08/2012
Block Plan            Approved        26/12/2012    
TPAK            Approved      21/11/2012
TPKB1              Approved        19/12/2012
TPKB 2              Approved        27/02/2013
Ijin Pondasi (IP)        Target Approval    15/05/2013
TPIB                  Target Approval    26/06/2013
Ijin Struktur Menyeluruh    Target Approval    15/07/2013
AMDAL            Target Approval    15/08/2013
PKS (SIPPT Compliance)    Target Approval    15/08/2013    
IMB                  Target Approval    30/08/2013
Pertelaan Gov Approval    Target Approval    30/09/2014
SLF                Target Approval            30/03/2015
Strata Title Certificate        Target Approval    30/06/2015

Notes:   
1. New regulation requires approval of KA-ANDAL in order to have Ijin Pondasi
2. PKS is a new authority requirement.

0



0
0
Meeting Rooms
Hotel Block
BACK ACCESS ROAD PROGRESS
B.2 BACK  ACESS ROAD




0

WIDYA CHANDRA
Complex
KRUKUT RIVER
SATRIA MANDALA 
MUSEUM Complex
BACK ACCESS
SIDE ACCESS
JL. GATOT SOEBROTO
ST REGIS JAKARTA
BACK ACCESS MAP
































Saturday, February 20, 2016

THE PRIORITIES IN THE CONTRACT BETWEEN SPEC, DRAWING AND BQ


1) Lump Sum Contracts

Generally SRJ Contracts are Lump Sum which means the contract sum is based on the requirements of the specs and the drawings 
The Drawings and specs are to be complied with (the BQ’s are just a tool for use in calculating monthly progress payments and for unit rates to be applied to variations)

The contractor has to install what is shown on the spec and drawings for the price in the BQ. 
If there are discrepancies  between Drawings / Specs and BQ (quantities or descriptions) there is no adjustment to the Contract sum (plus or minus)

That said if there are changes between the “Contract drawings” and the ”For Construction Drawings” only the differences between the two sets are measured and valued using appropriate BQ unit rates 
The VO issuing the “for construction” drawings is the only VO that needs to be issued



2) Provisional Quantities within Lump Sum Contracts

In the case of SRJ the following sections are noted in the LOA as Provisional Quantities 
a)      Plumbing pipework and fittings
b)      ACV pipework and fittings
c)      ACV ductwork and fittings
These  provisional quantities are to be re-measured jointly between LSI, GRU and Ssangyong using the Beca “for construction” drawings and the standard method of measurement bound into the contract

The actual types of pipe / duct and fittings will be measured and the appropriate unit rate in the BQ will be applied to the agreed quantities
The Provisional quantities in the BQ will be deleted

The only VO that needs to be issued is the one covering the issue of the “for construction” drawings

This approach only applies to items that are notated as “Provisional” in the contract BQ or the LOA



I list below a number of examples of the above for guidance of the team

EXAMPLES

A) RE-MEASURABLE CONTRACT
If Re-measurable the quantities in the BQ are the basis of the contract 
The entire works should be re-measured and  priced at BQ rates and the result replaces the quantities and price in the BQ 

1.      Tender drawings show item but item not in Bill, and construction drawings show same quantity with tender drawing without any changes. 
Quantities shown on “for con” drawings are measured and priced – these replace quantities and rates in the BQ

2.      Tender drawings didn’t show the item but Bills show some quantity. The construction drawings show different quantity to Bills. 
Quantities shown on “for con” drawings are measured and priced ( in this case nil)– these replace quantities and rates in the BQ

3.      Tender drawings show item but the item is not in construction drawings. Bills show the quantity.
Quantities shown on “for con” drawings are measured and priced ( in this case nil)– these replace quantities and rates in the BQ

4.      Tender drawings show 10 nos but tender bill shows 12 nos. and the construction drawings show 10 nos. 
Quantities shown on “for con” drawings are measured and priced ( in this case 10 nos)– these replace quantities and rates in the BQ

5.      Tender drawings show 10 nos but tender bill shows  8 nos, and the construction drawings show 10 nos. 
Quantities shown on “for con” drawings are measured and priced ( in this case 10 nos)– these replace quantities and rates in the BQ

6.      Tender drawings show 10 nos but tender bill shows 8 nos, and the construction drawings show 7 nos.
Quantities shown on “for con” drawings are measured and priced ( in this case 7  nos)– these replace quantities and rates in the BQ

7.      Tender drawings show 10 nos but tender bill shows 0 nos , and the construction drawings show 12 nos.
Quantities shown on “for con” drawings are measured and priced ( in this case 12 nos)– these replace quantities and rates in the BQ


B) LUMP SUM CONTRACT
If a Lump Sum contract the quantities in the BQ have no contractual significance and the contract sum is deemed to be based on drawings and specs 
If there are changes the value of the works should be adjusted by measuring the only the difference between tender / contract drawings and the “For Con” drawings

1.      Tender drawings show item but the item is not in Bill, and construction drawings show same quantity with tender drawing without any changes. 
Quantities shown on “tender / contract ” drawings are the basis of the contract . If there is no change between “tender/contract”  drawings and “for con” drawings then there is no variation or adjustment to the contract sum (regardless if there are any quantities in the BQ or not)

2.      Tender drawings didn’t the show the item but Bills show some quantity. The construction drawings show different quantity to Bills. 
Quantities shown on “tender / contract ” drawings are the basis of the contract . If there is a change between “tender/contract”  drawings and “for con” drawings then that difference is a variation and adjustment to the contract sum is applicable (regardless of the quantities in the BQ)

3.      Tender drawings show the item but the item is not in construction drawings. Bills show the quantity.
Quantities shown on “tender / contract ” drawings are the basis of the contract .In this case there is a change between “tender/contract”  drawings and “for con” drawings (the work has been deleted)  so the difference is a variation and adjustment to the contract sum is applicable (negative) (regardless of the quantities in the BQ)

4.      Tender drawings show 10 nos but tender bill shows 12 nos. and the construction drawings show 10 nos. 
Quantities shown on “tender / contract ” drawings are the basis of the contract . If this case there is no change between “tender/contract”  drawings and “for con” drawings - So no adjustment to the contract sum is applicable (regardless of the quantities in the BQ)

5.      Tender drawings show 10 nos but tender bill shows  8 nos, and the construction drawings show 10 nos. 
Quantities shown on “tender / contract ” drawings are the basis of the contract . If this case there is no change between “tender/contract”  drawings and “for con” drawings - So no adjustment to the contract sum is applicable (regardless of the quantities in the BQ)

6.      Tender drawings show 10 nos but tender bill shows 8 nos, and the construction drawings show 7 nos.
Quantities shown on “tender / contract ” drawings are the basis of the contract .In this case there is a change between “tender/contract”  drawings and “for con” drawings (the work has been reduced by 3 no)  and that difference is a variation and adjustment to the contract sum is applicable (negative 3 nos) (regardless of the quantities in the BQ)

7.      Tender drawings show 10 nos but tender bill shows 0 nos , and the construction drawings show 12 nos.
Quantities shown on “tender / contract ” drawings are the basis of the contract .In this case there is a change between “tender/contract”  drawings and “for con” drawings (the work has been increased by 2 nos)  and that difference is a variation and adjustment to the contract sum is applicable (additional 2 nos) (regardless of the quantities in the BQ)


C) LUMP SUM CONTRACT BUT PROVISIONAL QUANTITY (AS SRJ)
If the item or group of items in a Lump Sum Contract BQ or LOA are noted “Provisional” then those items (and only those items) should be treated as re-measurable (see Items A1-7 above)



Hope this helps

Regards

Steve Osborne
Langdon & Seah