MEP WORKS SEQUENCING in ST REGIS - FOUR SEASON -CAPITAL PLACE JAKARTA

SEQUENCING OF MEP WORKS
I. MEP 1st Fix 
1. Builder's work, Sleeves, Openings                
2. Exposed Conduit for Elect.                    
3. Installation of Cable Tray for Elect.
4. Exposed Conduit for ELV 
5. Installation of G.I. Trunking for ELV                 
6. Drainage Pipe work                               
7. Water Supply Pipe work
8. Gas Pipe work 
9. Fire Fighting Pipe work  
10. Pre-Insulated Duct Installation                  
11. Chilled Water Pipe Riser                         
12. Installation of Pressurization Duct              
13. Chilled Water Pipe work                       
14. Partial testing

II. MEP 2nd Fix 
1. Wiring for Lighting & Power                      
2. DB & Isolator Installation                       
3. Termination of DB's.                             
4. Cabling from DB's to SMDB's.                     
5. Cable Termination                                
6. MCC Installation & Cabling to Motors             
7. Cables Installation for Telephone & Data         
8. Cables Installation for Fire Alarm               
9. Cables Installation for BMS                      
10. Cables Installation for CCTV & A.V.
11. Cables Installation for MATV                     
12. Cables Installation for Public Address           
13. Cables Installation for Card Access              
14. Bus Duct Installation                            
15. Earthing works                                   
16. Install transformer
17. Install generator set
18. Drain & Cleanout works                           
19. Water Piping Accessories Installation                  
20. Fire Piping Accessories Installation                   
21. Fire Hose Cabinet Installation      
22. Install Pumps & Accessories                      
23. Gas Piping Accessories Installation                   
24. Install Gas vessels & Ancillaries                
25. Ducting Accessories Installation                      
26. Insulation for Chilled Water Pipe works          
27. FCU/AHU Installation                             
28. Jet Fan Installation                             
29. Smoke Exhaust Fan Install                        
30. Exhaust Fan Install                              
31. Fresh Air & Treated Fresh Air Fans Installation  
32. CHW Pressurization Fan Install                   
33. PCWRP Primary Chilled Water Pump Install         
34. Partial testing

III. MEP Final Fix 
1. Wiring Devices Installation                      
2. Light Fixture Installation                       
3. Sanitary wares Installation                      
4. Fire Extinguisher/Devices Installation           
5. Installation of Telephone & Data Devices         
6. Installation of Fire Alarm Devices & FACP        
7. Installation of BMS Devices                      
8. Installation of CCTV & A.V.(By Others) Devices   
9. Installation of MATV Devices                     
10. Installation of Public Address Devices           
11. Installation of Card Access Devices              
12. Diffuser and Grille

IV. Testing & commissioning
Testing & Comm. for Electrical works             
Testing & Comm. for Water supply works           
Testing & Comm. for Drainage works               
Testing & Comm. for H.V.A.C. works               
Testing & Comm. for Fire Fighting works          
Testing & Comm. for Telephone & Data works       
Testing & Comm. for Fire Alarm works             
Testing & Comm. for BMS works                    
Testing & Comm. for CCTV works                   
Testing & Comm. for MATV works                   
Testing & Comm. for Public Address works         
Testing & Comm. for Card Access works            
Testing & Comm. of Generator  Sets               
Testing & Comm. of Audio/Video System(By Others) 
Testing & Comm. of UPS System      

FB-GRU-St. Regist| Sequencing of MEP Works