Powered By Blogger

Sunday, February 21, 2016

ST REGIS PROJECT - CAPITAL PLACE










0
0
ST REGIS JAKARTA
PROJECT WILL COMPLETE BY 
JUNE 30, 2015 !!!!
0



0
Contents


A.Project Update
   A.1     Scope of Main Contractor
   A.2     Site Progress Photograph
   A.3     Piling Work Progress
   A.4    Main Contract Tender
   A.5     Mock Up 
   A.6     Tender Schedule for All Packages
   A.7     Project Milestone
   A.8     Design Status
   A.9     Site Logistic Layout Plan
   
CONTENTS
CONTENTS


A.Permit and Licenses
   B.1     Achievement & Target
   B.2    Back Access Road    C.1 Loan agreement    
Loading...



      A.   PROJECT UPDATE
ST REGIS JAKARTA    -  section A
0



ST REGIS JAKARTA
A.1. SCOPE OF MAIN CONTRACTOR
Main Contract Works:

Fixed price lump sum contract
Mock up room by main contractor
Earthworks, concrete works, structural steel work, roofing, waterproofing, block work and basic finishes.
MEP ,  Facade and all other packages also by main contractor as long as pricing is competitive.
Coordinate the overlap piling contract works (ACSET)
Coordinate ground anchor installation during basement excavation (VSL)
0
Loading...



ST REGIS JAKARTA

A.2. SITE PROGRESS PHOTOGRAPHS AS OF 22 APRIL 2013
PILING ACTIVITY ON SITE 
0



ST REGIS JAKARTA
‘D’ wall panel fabrication in progress
Rebar stock yard
‘View of Site From Top of Ramp

‘View of Site From Jl. Gatot Soebroto side
0



ST REGIS JAKARTA
Service  crane supporting concreting activities
Sludge management hindred by rainfall impact and upon site operation
‘D’ wall excavation in progress along Jl. Gatot Soebroto side
‘D ‘ wall excavation in progress along Idola Tunggal side
0



ZONING AREA
A.3 PILE ZONING PLAN
OFFICE
HOTEL
PODIUM
0
ST REGIS JAKARTA



0
ST REGIS JAKARTA
A.3 PILING WORK PROGRESS AS OF 24 APRIL 2013

BORED PILE

















AREA
Qty Plan (pile)
Done
Remaining
Status
Ahead (+)
Behind (-)
(Days)
Target Completion
Contract Completion Date


ZONE - 1 (OFFICE)
414
314
100
+44 
15 May 2013
28 June 2013


ZONE - 2 (PODIUM)
193
28
165
-8
06 July 2013


ZONE - 3 (HOTEL)
194
24
170
+15 
13 June 2013


TOTAL
801
366
435
-8
06 July 2013











D-WALL
AREA
Qty Plan (panel)
Done
Remaining
Status
Ahead (+)
Behind (-)
(Days)
Target Completion
Contract Completion Date
ZONE - 1 (OFFICE)
32
17
15
+45 
14 May 2013
28 June 2013
ZONE - 2 (PODIUM)
26
0
26
-10
08 July 2013
ZONE - 3 (HOTEL)
28
6
22
+15 
13 June 2013
TOTAL
86
23
63
-10
08 Juli 2013




= NEW PILE
= EXISTING PILE
PILING LAYOUT PLAN
ST REGIS JAKARTA
Loading...



A.4 MAIN CONTRACT TENDER
#1 Submission Participants  
 (Opened 11 March 2013)
1.PT. Balfour Beatty Sakti
2.Grocon (JV) PT. Nusa Raya Cipta
3.PT. Leighton Contractor Indonesia
4.PT. Nusa Konstruksi Engineering
5.PT. SsangYong
6.PT. Tata Mulia Nusantara Indah 

#2 Submission Participants  
 (Opened 8 April 2013)
7.PT. Balfour Beatty Sakti
8.Grocon (JV) PT. Nusa Raya Cipta
9.PT. Leighton Contractor Indonesia
10.PT. Nusa Konstruksi Engineering
11.PT. SsangYong
12.PT.Tata Mulia Nusantara Indah  (Declined)



       
#3 Submission Participants  
 (Opened 22 April 2013) – 3 Best Price
1.Grocon (JV) PT. Nusa Raya Cipta
2.PT. Nusa Konstruksi Engineering
3.PT. SsangYong




Planned  
Main Contract Award 
30 April 2013



       

C O N F I D E N T I A L 
ST REGIS JAKARTA
0



Plywood Mock Up Study was completed on Oct 2012, inspected on 10 Dec 2012 and demolished on Jan 15 2013






Real Mock Up will be built
    by Main Contractor and 
  complete by 30 June 2013





       
ST REGIS JAKARTA

A.5 MOCK UP 
0



ST REGIS JAKARTA
A.6 TENDER SCHEDULE FOR ALL PACKAGES

TENDER SCHEDULE








No.
Tender Name
Start
Finish


1
Demolition Work 
Done
09 Jun '12


2
Ground Anchor and Soil Nailing Work
Done
08 Sep '12


3
Bore Pile and Retaining Wall Work
Done2
28 Nov '12


4
Main Contract
11 Jan '13
30 Apr '13


5
Façade (part of Main Contract scope if price competitive)
11 Apr '13
02 Jul '13


6
MEP (part of Main Contract scope if price competitive)
4 May ’13
27 Aug‘13


7
Associated equipment with MEP (part of Main Contract scope if price competitive)
28 Apr ’13
31 Mar ‘14


8
Building Maintenance Unit (Gondola) (part of Main Contract scope if price competitive)
23 Sep '13
03 Jan '14


9
Interior Works of Hotel (part of Main Contract scope if price competitive)
13 Dec '13
22 Aug '14


10
Interior works Office (part of Main Contract scope if price competitive)
15 Apr '14
15 Aug '14













0



ST REGIS JAKARTA
A.7 PROJECT MILESTONES









No.
Milestones
Date


1
LoA Main Contractor
30 Apr 2013


2
Completion of piling works zone 1 (Office Tower area)
15 May 2013


3
Excavation commencement
21 May 2013


4
Hand over all area from piling contractor
28 Jun 2013


5
Structure Ground Floor Office Tower complete
28 Dec 2013


6
Topping off Hotel
30 Jun 2014


7
PLN energized
10 Aug 2014


8
Completion of facade works - Hotel
24 Aug 2014


9
Topping off Office Tower
10 Dec 2014


10
Partial Taking Over BOH (on Bsmt 1 & Bsmt 2)
30 Jan 2015


11
Partial Taking Over FOH  (on Bsmt 1 M for staff & lev.3 for GM)
30 Jan 2015


12
Completion of facade works - Office Tower
06 Feb 2015


13
Project Completion
30 Jun 2015






0



CONSULTANT      CONCEPT     SCHEMATIC    DESIGN     TENDER    TARGET
               DEV             DOC    DATE
a.PCPA (Architect)    √     √    √                        
b. Airmas Asri (Architect)     √     √    √     √    5/2/13
c. Beca MEP/PT.BK     √     √     √     √    4/5/13
d. Beca Structure/Gistama     √     √     √     √    5/2/13
e. Champalimaud (ID)     √     √    progress        14/1/13
f.  Bensley Design (Landscape)       progress                23/10/13
g. CCW (Acoustic)     √     √     √     √    23/11/13
h. BSLD (Lighting)     √     √     √     √    18/11/13
ii.PT. LSI (QS)     √     √     √    progress
j. DSI-TTW (Façade)     √     √     √     √    29/4/13
k. PT. Geo Optima (Geotech)     √     √     √        
l. CKP Hospitality (Kitchen)     √     progress            26/12/13
m. Tess Neoh (SPA)     √     √    progress    
n. PT. Velo (IT)     √    progress            24/1/14
o. PT. Wiragardha (Security & FLS)     √     √    progress        15/11/13
p. PT. Airkon Pratama (Greenship)     √     √    progress    
q. VADI (Signage)    progress                24/3/14
r. CPP (Wind Tunnel)     √     √     √     √



       
ST REGIS JAKARTA

A.8 DESIGN STATUS
0



A.9  SITE LOGISTIC LAYOUT PLAN

JL. GATOT SOEBROTO
0
GRU & CM Site Office
Mock Up Location
Main Con Site Office

Ramp to site offices
Car park
VIP Car park
Motorcycle park
PT. Acset site office

Car park
ST REGIS JAKARTA



0
ST REGIS JAKARTA
A.9 GRU AND CM SITE OFFICE

2nd Floor
GRU Site Office
1st  Floor
CM Site Office



0
ST REGIS JAKARTA
A.10 PROJECT COST UPDATE

Based on DLS cost plan Dec 2012 with zero amount contingency.



0
PERMITS  -  section B
      B.   PERMITS AND LICENSES
0



ST REGIS JAKARTA
B.1 PERMITS AND LICENSES ACHIEVEMENT AND TARGET
               Status        Completion
KKOP            Approved        16/03/2012
Plot Ratio Increment        Approved        24/07/2012
SIPPT            Approved        23/08/2012
Block Plan            Approved        26/12/2012    
TPAK            Approved      21/11/2012
TPKB1              Approved        19/12/2012
TPKB 2              Approved        27/02/2013
Ijin Pondasi (IP)        Target Approval    15/05/2013
TPIB                  Target Approval    26/06/2013
Ijin Struktur Menyeluruh    Target Approval    15/07/2013
AMDAL            Target Approval    15/08/2013
PKS (SIPPT Compliance)    Target Approval    15/08/2013    
IMB                  Target Approval    30/08/2013
Pertelaan Gov Approval    Target Approval    30/09/2014
SLF                Target Approval            30/03/2015
Strata Title Certificate        Target Approval    30/06/2015

Notes:   
1. New regulation requires approval of KA-ANDAL in order to have Ijin Pondasi
2. PKS is a new authority requirement.

0



0
0
Meeting Rooms
Hotel Block
BACK ACCESS ROAD PROGRESS
B.2 BACK  ACESS ROAD




0

WIDYA CHANDRA
Complex
KRUKUT RIVER
SATRIA MANDALA 
MUSEUM Complex
BACK ACCESS
SIDE ACCESS
JL. GATOT SOEBROTO
ST REGIS JAKARTA
BACK ACCESS MAP
































No comments:

Post a Comment