ST REGIS JAKARTA

PROJECT WILL COMPLETE BY
JUNE 30, 2015 !!!!
JUNE 30, 2015 !!!!
0

0
Contents
A.Project Update
A.1 Scope of Main Contractor
A.2 Site Progress Photograph
A.3 Piling Work Progress
A.4 Main Contract Tender
A.5 Mock Up
A.6 Tender Schedule for All Packages
A.7 Project Milestone
A.8 Design Status
A.9 Site Logistic Layout Plan
CONTENTS
CONTENTS
A.Permit and Licenses
B.1 Achievement & Target
B.2 Back Access Road C.1 Loan agreement
Loading...

A. PROJECT UPDATE
ST REGIS JAKARTA - section A
0

ST REGIS JAKARTA
A.1. SCOPE OF MAIN CONTRACTOR

Main Contract Works:
●Fixed price lump sum contract
●Mock up room by main contractor
●Earthworks, concrete works, structural steel work, roofing, waterproofing, block work and basic finishes.
●MEP , Facade and all other packages also by main contractor as long as pricing is competitive.
●Coordinate the overlap piling contract works (ACSET)
●Coordinate ground anchor installation during basement excavation (VSL)
0
Loading...

ST REGIS JAKARTA


A.2. SITE PROGRESS PHOTOGRAPHS AS OF 22 APRIL 2013

PILING ACTIVITY ON SITE
0




ST REGIS JAKARTA
‘D’ wall panel fabrication in progress
Rebar stock yard
‘View of Site From Top of Ramp

‘View of Site From Jl. Gatot Soebroto side
0





ST REGIS JAKARTA
Service crane supporting concreting activities
Sludge management hindred by rainfall impact and upon site operation
‘D’ wall excavation in progress along Jl. Gatot Soebroto side
‘D ‘ wall excavation in progress along Idola Tunggal side
0


ZONING AREA
A.3 PILE ZONING PLAN
OFFICE
HOTEL
PODIUM
0
ST REGIS JAKARTA


0
ST REGIS JAKARTA
A.3 PILING WORK PROGRESS AS OF 24 APRIL 2013

BORED PILE
| ||||||||
AREA
|
Qty Plan (pile)
|
Done
|
Remaining
|
Status
Ahead (+)
Behind (-)
(Days) |
Target Completion
|
Contract Completion Date
| ||
ZONE - 1 (OFFICE)
|
414
|
314
|
100
|
+44
|
15 May 2013
|
28 June 2013
| ||
ZONE - 2 (PODIUM)
|
193
|
28
|
165
|
-8
|
06 July 2013
| |||
ZONE - 3 (HOTEL)
|
194
|
24
|
170
|
+15
|
13 June 2013
| |||
TOTAL
|
801
|
366
|
435
|
-8
|
06 July 2013
| |||
D-WALL
AREA
Qty Plan (panel)
Done
Remaining
Status
Ahead (+)
Behind (-)
(Days)
(Days)
Target Completion
Contract Completion Date
ZONE - 1 (OFFICE)
32
17
15
+45
14 May 2013
28 June 2013
ZONE - 2 (PODIUM)
26
0
26
-10
08 July 2013
ZONE - 3 (HOTEL)
28
6
22
+15
13 June 2013
TOTAL
86
23
63
-10
08 Juli 2013


= NEW PILE
= EXISTING PILE
PILING LAYOUT PLAN
ST REGIS JAKARTA
Loading...

A.4 MAIN CONTRACT TENDER
#1 Submission Participants
(Opened 11 March 2013)
1.PT. Balfour Beatty Sakti
2.Grocon (JV) PT. Nusa Raya Cipta
3.PT. Leighton Contractor Indonesia
4.PT. Nusa Konstruksi Engineering
5.PT. SsangYong
6.PT. Tata Mulia Nusantara Indah
#2 Submission Participants
(Opened 8 April 2013)
7.PT. Balfour Beatty Sakti
8.Grocon (JV) PT. Nusa Raya Cipta
9.PT. Leighton Contractor Indonesia
10.PT. Nusa Konstruksi Engineering
11.PT. SsangYong
12.PT.Tata Mulia Nusantara Indah (Declined)
#3 Submission Participants
(Opened 22 April 2013) – 3 Best Price
1.Grocon (JV) PT. Nusa Raya Cipta
2.PT. Nusa Konstruksi Engineering
3.PT. SsangYong
Planned
Main Contract Award
30 April 2013
C O N F I D E N T I A L
ST REGIS JAKARTA

0

•Plywood Mock Up Study was completed on Oct 2012, inspected on 10 Dec 2012 and demolished on Jan 15 2013
•Real Mock Up will be built
by Main Contractor and
complete by 30 June 2013
ST REGIS JAKARTA


A.5 MOCK UP

0

ST REGIS JAKARTA
A.6 TENDER SCHEDULE FOR ALL PACKAGES

TENDER SCHEDULE
| |||||
No.
|
Tender Name
|
Start
|
Finish
| ||
1
|
Demolition Work
|
Done
|
09 Jun '12
| ||
2
|
Ground Anchor and Soil Nailing Work
|
Done
|
08 Sep '12
| ||
3
|
Bore Pile and Retaining Wall Work
|
Done2
|
28 Nov '12
| ||
4
|
Main Contract
|
11 Jan '13
|
30 Apr '13
| ||
5
|
Façade (part of Main Contract scope if price competitive)
|
11 Apr '13
|
02 Jul '13
| ||
6
|
MEP (part of Main Contract scope if price competitive)
|
4 May ’13
|
27 Aug‘13
| ||
7
|
Associated equipment with MEP (part of Main Contract scope if price competitive)
|
28 Apr ’13
|
31 Mar ‘14
| ||
8
|
Building Maintenance Unit (Gondola) (part of Main Contract scope if price competitive)
|
23 Sep '13
|
03 Jan '14
| ||
9
|
Interior Works of Hotel (part of Main Contract scope if price competitive)
|
13 Dec '13
|
22 Aug '14
| ||
10
|
Interior works Office (part of Main Contract scope if price competitive)
|
15 Apr '14
|
15 Aug '14
| ||
0

ST REGIS JAKARTA
A.7 PROJECT MILESTONES

No.
|
Milestones
|
Date
| ||
1
|
LoA Main Contractor
|
30 Apr 2013
| ||
2
|
Completion of piling works zone 1 (Office Tower area)
|
15 May 2013
| ||
3
|
Excavation commencement
|
21 May 2013
| ||
4
|
Hand over all area from piling contractor
|
28 Jun 2013
| ||
5
|
Structure Ground Floor Office Tower complete
|
28 Dec 2013
| ||
6
|
Topping off Hotel
|
30 Jun 2014
| ||
7
|
PLN energized
|
10 Aug 2014
| ||
8
|
Completion of facade works - Hotel
|
24 Aug 2014
| ||
9
|
Topping off Office Tower
|
10 Dec 2014
| ||
10
|
Partial Taking Over BOH (on Bsmt 1 & Bsmt 2)
|
30 Jan 2015
| ||
11
|
Partial Taking Over FOH (on Bsmt 1 M for staff & lev.3 for GM)
|
30 Jan 2015
| ||
12
|
Completion of facade works - Office Tower
|
06 Feb 2015
| ||
13
|
Project Completion
|
30 Jun 2015
| ||
0

CONSULTANT CONCEPT SCHEMATIC DESIGN TENDER TARGET
DEV DOC DATE
a.PCPA (Architect) √ √ √
b. Airmas Asri (Architect) √ √ √ √ 5/2/13
c. Beca MEP/PT.BK √ √ √ √ 4/5/13
d. Beca Structure/Gistama √ √ √ √ 5/2/13
e. Champalimaud (ID) √ √ progress 14/1/13
f. Bensley Design (Landscape) progress 23/10/13
g. CCW (Acoustic) √ √ √ √ 23/11/13
h. BSLD (Lighting) √ √ √ √ 18/11/13
ii.PT. LSI (QS) √ √ √ progress
j. DSI-TTW (Façade) √ √ √ √ 29/4/13
k. PT. Geo Optima (Geotech) √ √ √
l. CKP Hospitality (Kitchen) √ progress 26/12/13
m. Tess Neoh (SPA) √ √ progress
n. PT. Velo (IT) √ progress 24/1/14
o. PT. Wiragardha (Security & FLS) √ √ progress 15/11/13
p. PT. Airkon Pratama (Greenship) √ √ progress
q. VADI (Signage) progress 24/3/14
r. CPP (Wind Tunnel) √ √ √ √
ST REGIS JAKARTA
A.8 DESIGN STATUS

0


A.9 SITE LOGISTIC LAYOUT PLAN
JL. GATOT SOEBROTO
0
GRU & CM Site Office
Mock Up Location
Main Con Site Office
Ramp to site offices
Car park
VIP Car park
Motorcycle park
PT. Acset site office
Car park
ST REGIS JAKARTA

0
ST REGIS JAKARTA
A.9 GRU AND CM SITE OFFICE


2nd Floor
GRU Site Office
1st Floor
CM Site Office

0
ST REGIS JAKARTA
A.10 PROJECT COST UPDATE

Based on DLS cost plan Dec 2012 with zero amount contingency.

0
PERMITS - section B
B. PERMITS AND LICENSES
0

ST REGIS JAKARTA
B.1 PERMITS AND LICENSES ACHIEVEMENT AND TARGET

Status Completion
KKOP Approved 16/03/2012
Plot Ratio Increment Approved 24/07/2012
SIPPT Approved 23/08/2012
Block Plan Approved 26/12/2012
TPAK Approved 21/11/2012
TPKB1 Approved 19/12/2012
TPKB 2 Approved 27/02/2013
Ijin Pondasi (IP) Target Approval 15/05/2013
TPIB Target Approval 26/06/2013
Ijin Struktur Menyeluruh Target Approval 15/07/2013
AMDAL Target Approval 15/08/2013
PKS (SIPPT Compliance) Target Approval 15/08/2013
IMB Target Approval 30/08/2013
Pertelaan Gov Approval Target Approval 30/09/2014
SLF Target Approval 30/03/2015
Strata Title Certificate Target Approval 30/06/2015
Notes:
1. New regulation requires approval of KA-ANDAL in order to have Ijin Pondasi
2. PKS is a new authority requirement.
0

0
0
Meeting Rooms
Hotel Block
BACK ACCESS ROAD PROGRESS
B.2 BACK ACESS ROAD

0

WIDYA CHANDRA
Complex
KRUKUT RIVER
SATRIA MANDALA
MUSEUM Complex
BACK ACCESS
SIDE ACCESS
JL. GATOT SOEBROTO
ST REGIS JAKARTA
BACK ACCESS MAP